User:Franklin
From Group 4
Week 1 Report
What I did
- Worked on Project Spec/Schedule with the team
- Discussed direction and design of project with the group.
What I'm doing this week
- Working on networking between a client and server project.
- Constructing Config File (Likely XML)
- Creating logging construct to log all messages passed between client and server(w/timestamp).
- Making setup executable to modify Config file
What I'm doing next week
- Finishing whatever I didn't finish this week.
- Working with the Engine/Logic team to serialize and deserialize objects
Week 2 Report
What I did
- Created a basic network manager that can send messages from the server to the client
In Progress
- Managing the closing of connections (and updating the client table)
- Through explicit close client packets
- Through implicit could not find client error
What I'm doing this week
- Working on networking between a client and server project.
- Constructing Config File (Likely XML)
- Creating logging construct to log all messages passed between client and server(w/timestamp).
- Making setup executable to modify Config file
What I'm doing next week
- Finishing whatever I didn't finish this week.
- Working with the Engine/Logic team to serialize and deserialize objects